In an area covered by a local detailed plan, a building or its part may not be demolished without a permit as a rule. The permit is granted by the municipal building supervisory authority. The demolition permit is also required for buildings outside an area covered by a local detailed plan where a building prohibition is in force or if it is so stated in the local master plan.

Do the following

Describe in the permit application, in detail, how the demolition work will be organised and the building waste managed and whether usable components and parts can still be reused. Submit the permit application to the municipal building supervisory authority.

You can apply for a permit electronically through the Lupapiste.fi service.

Information on all service channels is not available in your chosen language. Change the language of the site to receive information on service channels in other languages.

To whom and on what terms

No permit is required if it is stated in a valid building permit or another decision issued by the authorities that the building must be demolished. Neither is a permit required for the demolition of an outbuilding or any other minor building, unless the building can be considered to be historically or architecturally important.

If the entrepreneur has established itself in another country in the European Economic Area and temporarily offers services in Finland, the same permits are required as from entrepreneurs established in Finland.


Period of validity

A demolition permit expires if the demolition work does not begin within three years after the permit is granted. However, the municipal building supervisor may extend the permit for two years at a time.

Background information

In an area covered by a local detailed plan, a building or its part may not be demolished without a permit. The permit is granted by the municipal building supervisory authority. The demolition permit is also required for buildings outside an area covered by a local detailed plan if a building prohibition is in force or if it is so stated in the local master plan.

Even if no permit is required for the demolition, the municipal building supervisory authority must be notified of the demolition 30 days before the start of the work.