Notification of the operation manager of the electrical installation

  • Permit or other obligation
  • Nationwide
  • Public service

The possessor of the electrical installation must appoint an operation manager of the installation when:

- the installation includes parts with a nominal voltage of more than 1000 V, such as a high-voltage transformer substation. This does not refer to installation supplied by a low-voltage electrical network (< or = 1000 V) that itself has high voltage

or when

- the connection capacity of the e ...

Do the following

The notification is filed electronically in the Regional Administration e-service.

Information on all service channels is not available in your chosen language. Change the language of the site to receive information on service channels in other languages.

To whom and on what terms

The operation manager must be a natural person with sufficient electrical competence (certificate of competence).

Changes concerning the possessor of the electrical installation and the operation manager must be notified to Tukes within one month of the change.


Deadline

The possessor of the electrical installation must submit a notification of the appointed operation manager to Tukes within three months of the deployment of the electrical installation.

Processing time

The preliminary processing time is 20 days.

Period of validity

Until further notice

The service is provided by

Finnish Safety and Chemicals Agency (Tukes)

Responsible for the service

Finnish Safety and Chemicals Agency (Tukes)
Text edited by: Finnish Safety and Chemicals Agency (Tukes)
Updated: 22/8/2023