The City of Tampere grants the deviation from the plans and the decisions on the alteration of the intended use. The application procedure is the same for both the planning requirement decision and the deviation decision.
Building contrary to an existing detailed plan, comprehensive plan or detailed shore plan requires a deviation permit. Before the actual building permit is issued, a building pr ...
Apply for a derogation from the municipality before applying for a building permit.
Include the following documents in your application:
State your reasons for applying and assess the potential impacts of your construction project.
Apply for a request about the need for a deviation decision or a planning requirement decision through the Lupapiste.fi. In the area with detailed plan, first contact the Building Control to determine is there need for the deviation decision. Apply for a deviation permit and planning requirement permit online at Lupapiste.fi. There must always be a justifiable reason for a deviation decision. In addition to a positive decision on a deviation or a planning requirement permit, you will always need a building permit.
If the entrepreneur has established itself in another country in the European Economic Area and temporarily offers services in Finland, the same permits are required as from entrepreneurs established in Finland.
The planning requirement permit, and the deviation decision are valid for the period specified in the decision, up to a maximum of two years.
In certain cases, applying for a building permit can require a derogation permit (i.e. a derogation decision) or an extended building permit review.
If a builder wishes to derogate from the plan or other provisions, regulations, prohibitions or other restrictions established in the Land Use Act and the Construction Act, such as the building code, they will need a derogation permit municipality before getting a building permit. In the derogation permit, the municipality indicates the period during which the builder must apply for a building permit. The period may not exceed two years.
If the builder is applying for a building permit for an area requiring planning, the municipality will consider the specific prerequisites for a building permit during the building permit process and conduct an extended building permit review. An area requiring planning is an area where, due to previous construction or other conditions in the area, special measures need to be taken, such as constructing roads, water pipes or sewers. The environmental effects of construction in an area requiring planning may also require the municipality to conduct a more extensive review than would be typical for a building permit process.
A derogation permit can only be granted if there is a specific reason for derogation.
The derogation must not have a negative effect on planning, a plan’s implementation or other use of the area. It must also not hinder the achievement of objectives related to nature conservation or protecting the built environment, result in construction with significant impacts, or otherwise cause significant harmful environmental effects or other effects.